On this page 8 sections
Each product page shows a production time: the working days between confirming your order and your parcel leaving us with the courier. Transit is extra, typically one to three working days more, and the count does not begin until both order and artwork are confirmed. Plan it in reverse: fix the day you need the print, then work back. That works the same for a Manchester shop opening as for an order heading to Cornwall.
Saver, Standard and Express
Whichever speed you pick, the product is identical: same material, same print, same finishing. What moves is the wait and the cost, with Express the dearest and Saver the least.
| Speed | Fastest products | Slowest products |
|---|---|---|
| Express | 1 working day | 16 |
| Standard | 2 | 17 |
| Saver | 4 | 19 |
Always read the figure for the specific product.
Typical production days
| Product | Express | Standard | Saver |
|---|---|---|---|
| Hoarding boards | 1 | 2 | 4 |
| Crowd barrier banners | 1 | 3 | 5 |
| Correx boards | 2 | 3 | 5 |
| Business cards | 2 | 3 | 5 |
| PVC banners | 2 | 4 | 6 |
| 850 mm roller banner | 2 | 4 | 6 |
| Mesh banners for Heras fencing | 4 | 6 | 8 |
| Dibond signs | 5 | 6 | 8 |
| NCR invoice books | 9 | 10 | 12 |
Mesh always lags PVC by two days. NCR books take a while at any speed, so order the next batch early. A few items, lamp-post wraps and fence-top signs among them, have a single 10-working-day time.
Working days only
A working day is Monday to Friday, excluding UK bank holidays. A job confirmed on a Thursday with a 3-day turnaround is ready on the Tuesday: Friday is day one, Monday day two, Tuesday day three. Each UK nation has its own bank holiday list (see GOV.UK), and the Easter and Christmas-to-New-Year periods remove several days, so look at the calendar before relying on Saver near them.
When the count begins
Payment alone does not start production; confirmation does, and your artwork route sets how fast that comes.
- Designed online: you signed the layout off on screen at checkout, so confirmation is instant. Best when time is short.
- Your own upload: we check dimensions, bleed and image quality free of charge. Clean files are confirmed at once; a file needing changes holds things up until the fix arrives.
- Artwork later: pay now, and we will email asking for the file. Day one comes after it lands and clears the check.
- Paid design: a first draft plus two rounds of changes, with the count beginning at your final approval.
Worked example: a shop opening in Altrincham
A new boutique opens on Saturday 5 December 2026 and wants a set of Correx window boards in hand by Thursday 3 December, leaving Friday to fit them. Correx boards take 5, 3 or 2 working days.
Step 1, transit. Budget the maximum three working days. Counting back from Thursday 3 December (Wednesday, Tuesday, Monday), the boards need to be dispatched on Monday 30 November.
Step 2, production. Call the confirmation date day zero and step back from 30 November:
| Speed | Days | Confirm by |
|---|---|---|
| Saver | 5 | Monday 23 November |
| Standard | 3 | Wednesday 25 November |
| Express | 2 | Thursday 26 November |
Step 3, artwork. Upload a day ahead of those dates so a file query costs nothing. Paid design needs extra days for the changes.
Confirming by 23 November gets identical boards at the Saver price; 26 November still works on Express.
Delivery comes after
Our part finishes at courier collection. You get a tracking email, and transit normally runs one to three working days; long or heavy parcels go by a specialist carrier and need signing for. Express shortens production, not transit. Mainland UK delivery costs £7.95 and is free when goods reach £100 after discounts; see the delivery page. You can also choose to collect from our Manchester office, and we email when the order is ready.
Tight dates
Plan mixed orders around the slowest item, leave a fitting day, and upload artwork with the order. Costs are in print prices explained, and the stages after payment in what happens after you order.
What else do people ask?
Does the production time include delivery?
No. It ends when the parcel leaves us; tracked transit adds roughly one to three working days.
Do weekends count?
Never. Only Monday to Friday count, and UK bank holidays are skipped.
Why has my order not started yet?
Usually because the artwork is not confirmed: a file query, a missing upload or a design version waiting for your reply. Clearing that restarts the plan.
Can you meet a date that looks too tight?
Possibly. Tell us the date through the contact page before ordering and we will give you a straight answer.