On this page 9 sections
Temporary fencing is built to let wind straight through. Cover a panel with solid plastic and you have made a sail sitting on two small feet. So the short answer for a banner on Heras fencing is: use mesh, tie through every eyelet, and get the fence installer's agreement before anything goes on. The same rules apply on a Wigan housing site, an Oldham road scheme or a festival perimeter anywhere in Greater Manchester.
Mesh or solid?
Heras panels are not fixed in the ground. Each one sits in two feet and is clamped to the next with couplers. Our Heras fence banners in mesh use 260gsm material full of tiny holes, so much of each gust passes through, yet from across the road the image reads as solid.
Solid is not ruled out. The PVC version is 440gsm PVC, or 400gsm PVC-free, and works in a sheltered spot, for a weekend event, or as a modest sign partway along a run. For weeks on an exposed site, choose mesh.
| Situation | Choose |
|---|---|
| Exposed site, months up | Mesh |
| Sheltered courtyard, short event | PVC or PVC-free |
| Small message mid-run | Either |
| General roadside fencing | Mesh banners |
Sizes against a standard panel
Most panels are about 3500 x 2000 mm (11ft 6in x 6ft 7in). Our sizes sit like this:
| Banner | Material | Effect on the panel |
|---|---|---|
| 3300 x 1800 mm | Mesh or PVC | Fills almost all of it, room to tie on every side |
| 3000 x 1500 mm | PVC | A big message with fence visible around it |
| 2000 x 1000 mm | PVC | A compact sign in the middle |
Hire companies' panels vary, so measure one first using our Heras fence panel size guide. The 3300 mm size is over 3 m, so the order pays the £15 oversize charge, once per order however many you buy.
Ask the fence owner before you start
This step is not optional. A banner changes how a fence behaves in strong wind, and panels blown flat across a pavement are dangerous. Call the company that installed or hired out the fence and ask whether it needs extra blocks on the feet or bracing on the panels carrying banners. On a managed site, get the site manager or principal contractor to approve the plan. The HSE construction pages cover site boundaries and temporary structures.
What to bring
- Banners with eyelets (metal lasts longer outdoors)
- One cable tie per eyelet, plus spares
- Side cutters
- Work gloves
- A helper
Fitting it
Expect about half an hour for the first panel and less after that.
- Agree the panels with the fence company or site manager, with any extra weights or bracing already in place.
- Check the fence. Each panel seated in its feet, couplers tight, run straight. Never use a leaning or bent panel.
- Lay the banner out and decide which side faces the road and which edge is the top.
- Tie the top corners to the top rail beside the uprights, the stiffest point, while your helper holds it.
- Tie the bottom corners to the lower rail so wind cannot get underneath.
- Tie every remaining eyelet, top, bottom, then sides. Skipping one overloads its neighbours.
- Tension evenly. Flat, not drum tight. Trim the tails and turn the heads to face the site.
- Check from the footpath. Nothing should overhang it and every panel should stand true.
Crowd barriers work the same way
The steel barriers used at fun runs and match days are dressed exactly like Heras panels. Crowd barrier covers come in 2200 x 800 mm, 2000 x 1000 mm and 2300 x 1000 mm, or a custom size from 500 to 2500 mm wide and 300 to 1200 mm high, in PVC, mesh or PVC-free. Measure one barrier and order slightly smaller than the frame. Production is 1 working day on Express, 3 on Standard and 5 on Saver.
Checks while the job runs
After any windy night, and at least weekly, look for:
- Broken ties. Replace them that day before the neighbouring eyelets tear.
- Shifting panels. Lifting feet, loose couplers or a leaning run should go straight to whoever manages the fence.
- Forecast storms. Cutting banners free until it passes is better than picking the fence up off the road.
Taking it down
Remove banners before the fence comes apart. Cut each tie, collect every offcut, dry the banner and roll it print side out. A mesh banner in good shape can go straight onto the next job; see how to store banners. For larger projects, browse site safety banners.
What else do people ask?
Can I put a solid PVC banner on Heras fencing in Manchester?
Yes, in a sheltered spot or for a short event. For exposed sites or long periods, mesh is much safer.
Do I really need to tie every eyelet?
Yes. Each missed eyelet adds load to the ones beside it, which is how eyelets tear and banners start flapping.
Who decides whether the fence can take a banner?
The fence installer or hire company, plus the site manager on a managed site. Ask them before fitting.
Can you suggest a size for my panels?